CBRE logo

Cleaning benchmark

global commercial real estate services firm · United Kingdom · 2025

A 100,000 sq ft headquarters benchmarked in three hours

ML10 produced a detailed cleaning specification for CBRE's 100,000 sq ft, seven-floor UK headquarters, capturing 9,400 assets. The conventional route was one surveyor on site for a full day followed by two days writing the specification — three days in total. With ML10 it took three hours, and cost £500 against £1,500.

MetricConventional routeWith ML10
Time to specification3 days3 hours
Cost£1,500£500
Assets capturedNot captured9,400
Site
UK headquarters, 7 floors
Size
100,000 sq ft
Assets captured
9,400
Year
2025

What this replaced

The point worth noticing is the third row of that table. The conventional route produces a cleaning specification and nothing else; the two days of survey effort leave behind a document and no data.

The ML10 recording produces the specification and an asset capture of 9,400 items from the same walk-through, at a third of the cost. The asset data is then available for contract pricing, maintenance planning and the next benchmark without anyone going back to site.

Outcome

A cleaning specification produced in an afternoon rather than across a working week, with an asset capture of the whole headquarters as a by-product of the same recording.

Reported by the client's Head of UK & US Procurement

Get Started

Ready to transform your FM contracts?

See ML10 Tech in action. A 30-minute demo on your portfolio — and we'll show you the savings.